特斯拉推出 Flex Connect 并网方案,超充站可先用现有电网容量开通、有望提前两年以上

Tesla unlocks faster Supercharger openings with new ‘Flex Connect’ system

AI 导读

特斯拉推出名为 Flex Connect 的超充并网方案:站点不再等电网扩容完工,先用现有电网容量开通运营,在用电高峰时段由电网公司临时下调站点可用功率,特斯拉称对车主感知影响很小、新站初期需求低时尤其如此。该方案有望让站点比原流程提前两年以上开通。特斯拉已与加州 PG&E 合作推进数个超充项目、另有数十个在推进中;其 V4 超充柜现可通过 IEEE 2030.5 标准与电网系统直连、按预测需求调节充电功率。数个试点站计划 10 月内开通,随后在北加州扩大推广。

正文

Tesla has introduced a new approach to connecting Superchargers to the electrical grid that could allow charging stations to open more than two years earlier than previously possible.

While Tesla has significantly reduced construction times for new Superchargers, getting enough power from local utilities remains a major challenge. This is particularly true for high-powered Megacharger stations designed for the Tesla Semi, where projects in Southern California can face grid connection delays exceeding three years.

Tesla believes it has found a way around that problem with a system called Flex Connect.

How Tesla’s Flex Connect system works

Instead of waiting for utilities to complete expensive and time-consuming grid upgrades, Flex Connect allows Superchargers to begin operating using existing electrical capacity.

When sufficient power is available, stations can operate at full capacity. During periods of high electricity demand, utilities can temporarily reduce the power available to the site.

Tesla says drivers should notice little difference, particularly at newer locations where charging demand is typically low.

The company has already been working with Pacific Gas and Electric (PG&E) in California, accelerating several Supercharger projects with dozens more underway.

Tesla also confirmed that its V4 Supercharger cabinets can now communicate directly with utility systems using the IEEE 2030.5 standard, allowing charging power to be adjusted based on forecast electricity demand.

Several pilot stations are scheduled to open in October, followed by a wider rollout in Northern California.

What could this mean for Canada?

The technology could eventually benefit Canada’s Supercharger network, particularly in smaller communities where electrical infrastructure may not have enough capacity to support a new high-powered charging station without significant upgrades.

Rather than waiting years for those improvements, Tesla could potentially open stations with reduced capacity and increase available power as the local grid is upgraded.

However, it is important to distinguish these situations from the delays experienced at several Canadian Supercharger locations.

Numerous Canadian projects have remained inactive for months, sometimes more than a year, after construction was completed. Those delays are not necessarily caused by insufficient grid capacity, but can also involve utility equipment availability, namely transformers.

Flex Connect would not resolve those issues if the equipment needed to safely energize a station is still missing.

Tesla has not announced any Canadian utilities participating in the program, but the technology could provide another option for expanding its charging network into smaller and more remote communities.

Related Articles:

Set Drive Tesla Canada as your preferred source

Always get the latest - make Drive Tesla your preferred source on Google

Are you buying a Tesla? If you enjoy our content and we helped in your decision, use our referral link to get three months of Full Self-Driving (FSD).

Drive Tesla uses affiliate links, which means we may earn a commission if you make a purchase through them, at no additional cost to you. Thank you for your support.

来源:MyTesla 编辑台 · driveteslacanada.ca