加拿大调查:市政审批拖慢充电桩建设,54 个站点签约后被放弃
New Survey Reveals Municipal Delays Slowing EV Charger Deployment Across Canada
加拿大充电基础设施委员会(CCIC)一项调查显示,市政审批要求正在拖慢公共充电项目。调查覆盖 9 家机构(7 家充电运营商或网络与 2 家施工承包商),业务遍及 8 个省;78% 的受访者认为市政停车位最低配建要求是延误来源,为最常提及的障碍;88% 称同一省内不同市政的审批流程存在中度到极大差异,安大略与魁北克被认为审批最慢。签署场地协议后,拿到市政许可通常需 3 至 6 个月,89% 的受访者认为停车场改造许可应在 3 个月内办结。过去 24 个月里,受访机构在签约后共放弃 54 个充电站点,其中 10 个主要归因于市政审批延误或驳回,另 17 个与电网接入延误或成本有关。CCIC 建议四项改革,包括把充电车位计入停车配建要求、简化改造审批、公布更明确的要求与确立 3 个月审批标准。调查于 2026 年 8 月 13 日至 9 月 3 日进行。
A new Canadian survey has found that municipal approval requirements are slowing public electric vehicle (EV) charging projects, even as more cities adopt EV-ready building rules.
According to the Canadian Charging Infrastructure Council (CCIC), 78% of respondents identified municipal parking minimum requirements as a source of delays, making them the most frequently cited obstacle.
The findings come from a survey of nine organizations, including seven charging operators or networks and two construction contractors, with deployment experience across eight provinces.
Meanwhile, 88% reported moderate to extreme differences in approval processes between municipalities within the same province. Ontario and Quebec were most frequently identified as having the slowest approvals (via MobileSyrup).
Most respondents said obtaining municipal permits typically takes three to six months after signing a site host agreement. However, 89% believe parking-lot retrofit permits should take less than three months.
These delays are also affecting completed projects. Over the preceding 24 months, respondents reported abandoning 54 charging sites after securing host agreements.
Of those, 10 were primarily attributed to municipal approval delays or denials, while another 17 were linked to utility connection delays or costs.
CCIC is recommending four changes, including recognizing charging stalls within parking requirements, streamlining retrofit approvals, publishing clearer requirements and establishing a three-month approval standard.
“Municipalities have a real opportunity to use private investment to advance their environmental, economic, and equity goals,” said Travis Allan, President and CEO of CCIC.
The survey was conducted between August 13 and September 3, 2026, with CCIC also publishing a companion municipal policy brief.
Related Articles
- Ivy expands ONroute charging network with more stations and upgrades
- Canada Launches New Alliance to Turn EVs Into Grid Batteries
- FLO Launches New EV Charging Rewards Program for Home and Public Charging
- Metro Vancouver is thousands of EV chargers short to meet demand: Report
Always get the latest - make Drive Tesla your preferred source on Google
Are you buying a Tesla? If you enjoy our content and we helped in your decision, use our referral link to get three months of Full Self-Driving (FSD).
Drive Tesla uses affiliate links, which means we may earn a commission if you make a purchase through them, at no additional cost to you. Thank you for your support.
来源:MyTesla 编辑台 · driveteslacanada.ca